Trump Tower Kolkata is targeting December for completion, nearly a decade after the luxury residential project was launched and more than six years after its original delivery deadline.
Developer Tribeca Developers said that construction is nearing completion and it plans to apply for a completion certificate from the Kolkata Municipal Corporation (KMC) by December. Handover to buyers is expected to take place in phases, subject to approvals and other formalities.
The 38-storey project, located off EM Bypass, was launched in 2017 by Unimark Group, RDB Group and Tribeca Developers. The developers had initially targeted delivery by mid-2020 and expected sales of around Rs 700 crore. However, the project remained unfinished and is still classified as “under construction” on the West Bengal Real Estate Regulatory Authority’s website.
According to Tribeca, the project is now substantially complete, with remaining work focused mainly on finishing apartments, recreational facilities and other amenities. The developer said the project has received its fire safety certificate, all lifts have been installed and the required lift licences have been obtained. House drainage permission has also been secured, although said it has not independently verified each approval.
The project has faced several delays over the years. Tribeca attributed them to the Covid-19 pandemic, supply-chain disruptions, difficulties in importing specialised materials and equipment, regulatory delays and a property-tax dispute with KMC. Construction activity was also temporarily suspended in Kolkata during June and July 2026.
The property-tax dispute involved a demand of around Rs 14 crore from KMC. Tribeca has challenged the demand in court while continuing discussions with civic authorities. The dispute had earlier affected the revalidation of the building plan and drainage-related approvals.
The project has 137 apartments, according to West Bengal RERA records. As of the quarter ended September 2024, 105 residential apartments had been booked.
With the developer now targeting December for the completion certificate application, buyers are awaiting formal possession after years of delays. The final handover will depend on completion of the remaining work and receipt of the required statutory approvals.